Customer

Ahrtal-Werke

Construction site

Bad Neuenahr

Industry

Provider

Client

Ahrtal-Werke

Order value

12.000.000 €

Customer requirement

Construction of a new combined heat and power plant to generate heat for the district heating network in Bad Neuenahr, as well as generating electricity via 2 natural gas generators as a by-product.

Technical details
  • 2 Medium-voltage switchgear in primary and secondary versions
  • 2 transformers with 1.6 MW each Busbar mounting between transformer and NSAV
  • Delivery and installation NSAV 2,500 ampere
  • Supply and installation Auxiliary power supply, designed as 400VAC and 60VDC
  • Low-voltage sub-distribution board for the
  • Building installation
  • General building installation, lighting with safety function, expansion of cable support systems and cable routes
Wir nutzen Cookies und Scripts auf unserer Website. Einige davon sind essenziell, während andere uns helfen, diese Website und Ihr Nutzererlebnis mit ihr zu verbessern.
Die Widerrufsmöglichkeit befindet sich in der Datenschutzerklärung. 
Individuell anpassen. Individuell anpassen.
Alle Akzeptieren